A contract manufacturing cost model adds up what one run costs you, then turns it into a fee the client pays for each unit. In a toll run the client supplies the ingredients and packaging, so those aren't your costs. Yours are four things: the labor of everyone on the line, the line's day (rent, power, equipment, insurance, the changeover, the paperwork), the materials you supply (cases, shrink bands, cleaning chemicals), and your margin. Divide by the units the run makes and you have the fee. The model also shows the thing clients argue about most, which is why a short run costs more a bottle. Below is the sum for a made-up co-packer quoting 5,000 bottles of a client's hot sauce, and a calculator.
The short version
- Count labor as people × hours × the wage with payroll taxes.
- The line's day costs the same whether it makes 3,000 bottles or 5,000.
- List every material you supply. Small ones add up.
- Fee = run cost ÷ units ÷ (1 − margin).
- Quote all in, or a fee for the work plus your materials at cost.
- State a minimum run, and what the client supplies.
- TaroStack keeps a client's goods apart from yours and bills the fee for each run. More below.
What the run costs you
The client delivers the sauce ingredients, bottles, caps and labels. The co-packer cooks, fills, bands, cases and palletizes 5,000 bottles in a day.
| Cost | How it's worked out | The run |
|---|---|---|
| Labor | 4 people × 7.5 hours × $24.00 | $720.00 |
| The line's day | Rent, power, equipment, insurance, changeover, paperwork | $520.00 |
| Shrink bands | 5,000 | $38.00 |
| Shipping cases, 12 bottles | 417 at $0.58 | $241.86 |
| Case labels | 417, at $12.00 for 500 | $10.01 |
| Cleaning chemicals and test strips | One run | $24.00 |
| Pallets and stretch wrap | $0.013 a bottle | $65.00 |
| The run | $1,618.87 | |
| A bottle | ÷ 5,000 | $0.324 |
Labor. Count everyone, including the person who cleans down afterward, and use what an hour really costs you: the wage plus payroll taxes. Here that's $24.00.
The line's day. This is the number people leave out. Take a year of rent, power, equipment payments, insurance and repairs for the production space, and divide by the days the line can run. This co-packer's comes to $65 an hour, $520 for an eight-hour day. A changeover and clean-down belong here too: the line makes nothing while it's being washed.
Your materials. Cases at $0.58 each look small. At $241.86 they're the largest thing you buy for the run.
"About 40 cents" would have left $381 on a $2,000 job, before anything went wrong.
From cost to fee
| Fee a bottle | The client pays | Left after the run's cost | Margin |
|---|---|---|---|
| $0.41 | $2,050.00 | $431.13 | 21% |
| $0.45 | $2,250.00 | $631.13 | 28% |
| $0.50 | $2,500.00 | $881.13 | 35% |
The margin is what pays for the days the line doesn't run, the client who cancels, the batch you have to redo. This co-packer quotes $0.45, would take $0.41 for a client who books a run every month, and opens at $0.50 for a one-off.
Two ways to write the same quote.
| All in | Fee plus materials | |
|---|---|---|
| Fee for the work, a bottle | $0.45 | $0.37 |
| Your materials | Included | At cost: $378.87 |
| The client pays | $2,250.00 | $2,228.87 |
The all-in fee is simpler to read. The split is safer for you: when case prices rise, the client's bill rises with them and the fee for the work stays what it was. On the split, the fee covers labor and the line's day, $1,240, and leaves $610.
Why a short run costs more
The client asks for 3,000 bottles at the same $0.45.
| 5,000 bottles | 3,000 bottles | |
|---|---|---|
| Labor | $720.00 | $504.00 |
| The line's day | $520.00 | $520.00 |
| Your materials | $378.87 | $227.32 |
| The run | $1,618.87 | $1,251.32 |
| A bottle | $0.324 | $0.417 |
| Left at $0.45 | $631.13 | $98.68 |
Materials fall with the bottle count. Labor falls less, because the setup and the clean-down take the same time either way: here, 21 hours instead of 30. The line's day doesn't fall at all, since nothing else can run on it that afternoon. So 3,000 bottles cost $0.417 each, and $0.45 leaves $98.68. That's the reason for a minimum run, or a higher fee below it. Showing the client this table works better than saying "that's our policy".
What else goes in the quote
- What the client supplies, by when, and who pays if it arrives short or late.
- An allowance for loss: bottles broken on the line, sauce left in the kettle.
- Storage after the run, and for how long it's free.
- A setup charge for the first run: a new label on the labeler, a process review, a test batch.
- Who buys what next time prices change.
The agreement behind the quote is in co-packing agreement template, the bill in tolling invoice template, and the same sum from the client's side in how much does a co-packer cost.
Get the calculator
Download the contract manufacturing cost model. Two sheets and a read-me: batch cost, from your materials, the minutes worked, the hourly wage and the line's day, down to the cost of one unit; and prices, where each fee shows what it leaves. It's an ordinary Excel file with no macros, and it works in Google Sheets, LibreOffice and Numbers.
Where this stops working
The quote is the easy part. Then the client's pallets arrive: 5,200 bottles, 60 gallons of pepper mash, two rolls of labels. They sit beside your own bottles and your own mash. Three runs later the client asks how many of their bottles you still have, what you used in October, and why the invoice says 4,900. A cost model has no answer. Those are stock questions about goods that aren't yours.
How TaroStack does it
TaroStack keeps a client's goods as the client's, and bills each run.
Every item says whose it is: yours, or a client's own. A client's goods are received at no cost to you, kept apart, and left out of your stock value and your margins.
A toll run is a batch for that client. It uses the client's goods and yours, never another client's, and records every material it used and whose each was.
The fee per unit made is set on the item. Billing a client puts the production fee and your materials at cost onto an ordinary sales order, each line naming its run, billed once.
A monthly statement for each client: their goods you hold and how each moved, by lot, and the month's charges.
| The job | Cost model and a notebook | In TaroStack |
|---|---|---|
| How many of their bottles are left | Count, and hope | Their goods, by lot |
| What October's runs used | Add up batch sheets | On each run's record |
| The bill for a run | Typed from the quote | Fee and materials, from the run |
| Their stock in your stock value | Mixed in | Left out |
TaroStack doesn't cost your labor or work out the fee: the model above does that. Storage billed by the pallet-month is typed onto the charges by hand. Working for clients is on Business at $89 a month, with 5 active clients. The first 14 days are free, with no credit card. If you'd like a hand setting up, ask, and we'll do it with you.