Change Control Log Example for a Small Food Maker

A change control log example: one row for each change to a recipe, supplier, label or process, the checks before it goes ahead, and a free template.

By Koa Sterling. Product specialist at TaroStack and small business owner. Yes, I am a real human, and I actually sit in front of a computer and write these articles. Reviewed November 21, 2026 · 6 min read

A change control log is a list of the changes you've made to how you make things, each written down before it happens, with one question answered: what else does this touch? A new almond supplier looks like a purchasing decision. It can also change your allergen statement, if the new supplier's plant handles peanuts and the old one's didn't. Cutting the honey looks like a recipe tweak. It can change the nutrition panel and the shelf life. The log is where those knock-on effects are caught, by making someone list the checks and sign that they were done. Each row has what's changing and why, what it touches, the checks needed first, who approved it, and the first batch made the new way. Below is a log for a made-up granola maker with three changes in it, what to check for each kind of change, and the template.

The short version

  • One row a change, raised before the change is made.
  • Say what's changing, why, and what it touches.
  • List the checks first: allergens, label, shelf life, cost, training.
  • One person approves, and signs.
  • Record the first batch or lot made the new way.
  • Close the row only when every check is done.
  • TaroStack keeps recipe versions and which batch used which. More below.

An example log

No. Raised What is changing What it touches Approved In effect from
CC-014 Oct 20 Almonds from a second supplier Recipe HA-12, allergen statement, cost Owner, Oct 27 Batch 26306-1
CC-015 Nov 3 Honey reduced from 6.5 lb to 6 lb a batch Recipe HA-12, nutrition panel, shelf life Owner, Nov 3 Batch 26307-2
CC-016 Nov 12 New 24 oz bag Packaging, net weight on the label, case pack, price list Open

And the columns that do the work, for the first two:

No. Why Checks before it went ahead Done and verified
CC-014 First supplier short until January New supplier's allergen statement read: its plant also handles peanuts. Label reviewed. Cost recalculated Yes, Nov 2
CC-015 Customer feedback: too sweet Trial batch tasted. Nutrition panel recalculated. Two bags held for shelf life Recipe and label updated. Shelf life check still open

CC-014 is the row that pays for the log. The almonds were the same almonds. What changed was where they were packed, and that was on the supplier's allergen statement for anyone who read it. The check made someone read it before the first delivery was opened, and the label was reviewed before the first bag shipped.

CC-015 isn't closed, and the log says so. The recipe and the label are done. The shelf life check is waiting on two bags in a cupboard. An open row is a job with a name on it.

What to check, by kind of change

The change Check before it goes ahead
A new supplier for an ingredient Its allergen statement and specification. Its lot coding. The cost
A different ingredient Allergens, the ingredient list and its order, nutrition, claims such as organic or gluten-free
More or less of an ingredient The ingredient order on the label, nutrition, shelf life
New packaging or size Net weight on the label, the barcode, the case pack, shelf life in the new pack
A process change: time, temperature, equipment Whether the product still meets your food safety plan's limits. Shelf life. Training
New equipment Cleaning procedure, allergen changeover, training
A new product on a shared line Allergens carried over from the other products

The list is a starting point, not a standard. If you're audited, your audit scheme may have its own requirements for managing change: use its wording. For changes that touch a critical limit, see HACCP plan summary and HACCP validation template.

How to run it

  1. Raise it first. The row is written when the change is proposed. A log filled in afterward is a diary.
  2. Number it. CC-014 is easier to write on a batch sheet than a sentence.
  3. List the checks before approving. Approval means the list is right, not that the idea is good.
  4. Name the first batch. "In effect from Batch 26306-1" draws a line: everything before it was the old way.
  5. Close it when the checks are done, with a date and initials.
  6. Review open rows monthly.

A recipe change is also a new recipe version: see what is recipe management. A supplier change belongs on the supplier list too: see approved supplier list and new vendor form template. Reading a supplier's allergen paperwork is in supplier questionnaire template.

Get the template

Download the change control log. One sheet and a read-me: eleven columns from the change's number to done and verified, with the granola maker's three rows as examples. It's an ordinary Excel file with no macros, and it works in Google Sheets, LibreOffice and Numbers.

Where this stops working

The log says CC-014 took effect from batch 26306-1. That's only useful if the batch records agree. On the floor, the old almonds and the new almonds were both open for a week, and three batches used whichever sack was nearer. The log draws a clean line. The lots that went into each batch drew a different one, and no one wrote that one down.

How TaroStack does it

TaroStack records what each batch actually used, so the line is where it really fell.

Recipes have versions. The honey change is version 4, with its date, and every batch records which version it used.

A batch notes the lots it used, automatically. A batch that took almonds from the new supplier's lot says so, whichever sack was nearer.

Each delivery is a lot with its supplier, so "the first batch with the new supplier's almonds" is a search.

Batch records carry your own checklist fields, so a check a change calls for is recorded with the batch.

Every lot is traced to the customers that got it.

The question The log alone In TaroStack
Which batch first used the new almonds The batch someone wrote down The first batch that took that lot
Which batches used recipe version 4 From the date, roughly Each batch's version
Who received those batches Invoices The recall report
Was the check done on that batch A tick in the log A field on the batch

TaroStack isn't a change control system: it doesn't raise, approve or close changes. Keep the log. Recipes, versions, batches and lots are on every plan, from $9.99 a month (5 recipes) or $39 a month (50 recipes). The first 14 days are free, with no credit card. If you'd like a hand setting up, ask, and we'll do it with you.

Questions people also ask

What is a change control log?

A record of each change to a recipe, supplier, packaging, label, equipment or process, written before the change is made, listing what it affects, the checks required, who approved it and when it took effect.

What should a change control log include?

A number, the date raised, what is changing and why, who raised it, what it touches, the checks needed first, who approved it and when, the first batch made the new way, and confirmation that the checks were done.

Why does a small food business need change control?

Because small changes have side effects. A new supplier can bring a new allergen risk, and a recipe change can make the label or the shelf life wrong. The log makes someone look before the change, not after a complaint.