Material Requirements Planning Example: An MRP Grid, Worked

A material requirements planning example: gross and net requirements, lot sizes, lead times and planned orders, worked for a granola maker, a free grid.

By Koa Sterling. Product specialist at TaroStack and small business owner. Yes, I am a real human, and I actually sit in front of a computer and write these articles. Reviewed October 17, 2026 · 6 min read

Material requirements planning (MRP) turns a production plan into a buying plan: how much of each ingredient and packaging item you need, and when to order it so it arrives in time. For each material and each week it works down six rows. Gross requirements: the runs planned that week times the amount per run. Scheduled receipts: orders already on their way. Net requirements: how much more you need to stay above your safety stock. Planned receipts: that need rounded up to the supplier's order multiple and minimum. Projected on hand: what's left at the end of the week. Planned order releases: the planned receipts moved back by the lead time, the week you place the order. The most useful thing an MRP grid shows is the order that's already late: something needed sooner than its lead time allows. In the example below, a granola maker plans six weeks before the holidays and finds two orders it should have placed already. Below are the rows, the example, and a free grid.

The short version

  • MRP turns a production plan into what to order and when.
  • Gross requirements = runs planned × amount per run.
  • Net requirements = what's needed beyond on hand, orders on the way and safety stock.
  • Planned receipts round the need up to the order multiple and minimum.
  • Planned order releases are the receipts moved back by the lead time.
  • An order needed sooner than its lead time is already late.
  • TaroStack plans what to make and what to buy on Standard at $99 a month. More below.

The rows

Row How it's worked out
Gross requirements Runs planned that week × the amount per run, from the recipe
Scheduled receipts Orders already placed, in the week they arrive
Net requirements Safety stock − (last week's on hand + scheduled receipts − gross requirements), if above zero
Planned receipts The net requirement rounded up to the order multiple, at least the minimum
Projected on hand Last week's on hand + scheduled receipts + planned receipts − gross requirements
Planned order releases Each planned receipt, moved earlier by the lead time

The production plan itself is in production schedule example, and the bill of materials behind "amount per run" in bill of materials for food.

An example: a granola maker before the holidays

Cache Valley Granola Co., the made-up granola maker in Logan, Utah, I use in these examples, makes granola in 120-pound runs of 150 bags and plans 2, 3, 3, 4, 4 and 5 runs over the next six weeks. Four materials:

Material Per run On hand Safety stock Order multiple Minimum Lead time
Rolled oats 52.8 lb 200 lb 50 lb 50 lb 50 lb 1 week
Almonds 14.4 lb 60 lb 25 lb 25 lb 25 lb 2 weeks
Honey 16.8 lb 90 lb 30 lb 60 lb pail 60 lb 1 week
Printed bags 150 600 300 500 2,000 3 weeks

The oats, worked through, with 500 pounds already arriving in week 2:

Oats, week 1 2 3 4 5 6
Gross requirements 106 158 158 211 211 264
Scheduled receipts 500
Net requirements 0 0 0 0 195 259
Planned receipts 0 0 0 0 200 300
Projected on hand 94 436 278 66 55 91
Planned order releases 200 300

The oats are fine: order 200 pounds in week 4 and 300 in week 5. The grid flags two problems. Almonds need 50 pounds by week 2 on a two-week lead time, so that order is already late; the supplier's rush delivery costs more but saves the runs. Printed bags need 2,000 by week 2 on a three-week lead time, and the 600 on hand cover only until then; the second order of 2,000 for week 5 goes in at week 2, and week 2's bags come from 150 plain kraft bags with stickers while the printer catches up. Honey needs a 60-pound pail every week through week 5. How the recipe and run are built is in how to make granola in bulk.

Get the grid

Download the MRP grid. One sheet: type the runs planned each week, and for each material its amount per run, on hand, safety stock, order multiple, minimum, lead time and any orders already on their way; gross and net requirements, planned receipts, projected on hand, planned order releases and anything already late fill in, with orders to place in red. It's an ordinary Excel file with no macros, and it works in Google Sheets, LibreOffice and Numbers.

Where this stops working

Six weeks and four materials fit on a sheet. Twelve products sharing thirty ingredients, plans that change on Monday, and lead times that slip make the grid stale before it's printed.

How TaroStack does it

TaroStack's planning works from your recipes, stock and suppliers, and says what to make and what to buy.

What to buy, from the plan. Planning works out what each planned batch needs from its recipe, against what's in stock and on order, and says what to buy and when, with each supplier's lead time and minimum.

Lead times checked against reality. What a supplier promises is compared with how long its deliveries really take, so a lead time that slips shows up before the grid is wrong.

The reorder list, on every plan. Without planning, the reorder list shows each item in days of cover, with each supplier's lead time and minimum, and reorder points suggested from how stock actually moves.

The job Spreadsheet In TaroStack
What a plan needs Runs × recipe, by hand From the recipes
What to order and when An MRP grid Planning's buying list
A late order Spotted, or not On the buying list, by date
Lead times What the supplier said Checked against deliveries

Planning, what to make and what to buy, is on Standard at $99 a month; recipes, batches and the reorder list are on every plan, from $49 a month. The first 30 days are free, with no credit card. If you'd like a hand setting up, ask, and we'll do it with you.

Questions people also ask

What is an example of material requirements planning?

A baker planning four runs next week multiplies each ingredient per run by four, subtracts what's on hand and on order, keeps a safety stock, rounds up to the supplier's case size and orders a lead time ahead.

How do you calculate net requirements in MRP?

Safety stock minus what you'll have after the week's use: last week's on hand plus orders arriving minus gross requirements; if that's above zero, it's the net requirement.

What is a planned order release?

The week you place an order so it arrives when needed: the planned receipt moved earlier by the supplier's lead time.

What is the difference between MRP and a reorder point?

A reorder point orders when stock falls to a level; MRP orders from the production plan, ahead of the runs that will use the stock.